| |
These are extracts from the Diaries being kept. Click on the extract of
interest below, to open the pages.
-
How we came to take on a Yacht Building Project.
-
The Hull 'Emerald' as we took the project on. February 1992.
-
Laminating BulkHeads, Bought Engine, Starting on Companionway. March/April 1992.
-
Working on Companionway, Cockpit sides and back, Deck ply inserts. May/June 1992.
-
Ply Inserts in Forward and Side Decks. July 1992.
-
Re-making of the Main Cabin Front. August 1992
-
Continuing with Main Cabin Front. September 1992.
-
Fixing in place the New Main Cabin Front. Making up New Main Cabin Coachroof Beams. September 1992.
-
Fitting in Main Coachroof beams. Making Companionway hatch frame. October 1992.
-
Completing fixing Main Cabin Coachroof beams and ply inserts. November 1992.
-
Starboard Deck ply Inserts completed. Redundancy Strikes. December 1992.
-
Making up Forward Hatch. Battening Forward Cabin Front. January/February 1993,
-
Battening outer Forward Cabin Sides. Getting the original Rudder & Shaft out. March/April 1993.
-
Forepeak Strengthening. Fitted Cockpit Sides. Start on remake of Rudder. May/June 1993.
-
Battening Main Cabin Outer Sides. Laying 2nd layer plywood on sides and aft deck. July/August 1993.
-
Moving House twice in three months. Starboard cabin side battens fixed in place. September to December 1993.
-
Land Owner wants us out !. Fixing in place the aft deck 2nd layer plywood. January to March 1994.
-
Fixing in place the covering boards. Search for alternative home for the Boat . April/May 1994.
-
Rudder completed enough to fit. Cockpit well sides fitted. Dropboards made. June/July 1994.
-
Preparations to move 'Emerald' to a proper Boatyard. August 1994.
-
Having to move 'Emerald' to a proper Boatyard. August 1994.
-
Levelling up the Hull. Epoxy coating on bare timber. Battling against the weather. September 1994.
-
Marina Charges go Up. Started Companionway Hatch area. Battening down for winter. October 1994 to January 1995.
-
Tying tarpaulin half naked!, making cockpit sole and cockpit hatch frame. February 1995 to May 1995.
-
Starting on Stainless Steel Tabernacle. Making up Companionway Hatch. June 1995 to July 1995.
-
Completion of Companionway Hatch and Runners. August 1995 to September 1995.
-
Making Hatch for a Canal Barge. Boat Yard Hassle. Companionway Hatch finishing touches. September 1995 to May 1996.
-
Continuing work on Tabernacle & Main Hatch.. High Marina Charges forces 2nd move. June 1996 to May 1997.
-
Getting levelled and setup again. Running the engine in the back garden. June 1997 to April 1998.
-
Repair Cradle, Prepare to Move & Tabernacle in the making 1999
-
Boat Move 2000, Replacing Platform Steps 2002, Work in Cockpit area, and buying Flexiteek 2003
-
Planing Covering board, Moving Emerald, in the Marina, yet again 2005
-
At long last - moving Emerald undercover, with workshop facilities. Fantastic.
* * UPDATE * * After finally
managing to get 'Emerald' back undercover during 2006, and the project was
making positive headway, it was tragic that the Captain/Boat
Builder/Master Carpenter passed away following a hereditary illness. Sadness
still overshadows the project, it is such a great loss to the project, but the
remaining crew member is determined to complete 'Emerald', launch her and
dedicate 'Emerald' in memory of the Captain.
-
Sanding inside, Making Workbenches, Cutting templates and plywood for decking.
-
Sticking down the last layer of Deck plywood & making up quadrants
-
Photos of latest progress
-
Steam bending, tooling deck cabin corners
-
Deck edgings progress
-
Tooling timber for cockpit coaming, Portlights going in
-
Cockpit coamings progress, planing timber for inner cockpit lats
-
Getting the engine, from home, onboard!....
-
Flexiteek Decking work, Deck fittings put in place. Galley construction and companionway steps in place....
-
literally levelling up to Launching!!....
-
The BIG day - The Launch!!....
/Diary>
Boat Building - Yacht Emerald Undergoing Construction
| |
|